Orders7 Oct 2026 · Wed
LTLarsen & Toubro
L&T arm gets a limited notice to proceed for two 800 MW units at Chandrapura in Jharkhand
L&T Energy CarbonLite Solutions received a limited notice to proceed from DVC CIL Power for the main plant package of the 2×800 MW Chandrapura thermal project, an order L&T put at up to ₹10,000 crore.
Price, Wednesday's close₹3,692.00▼ 2.07%
Last 5 days
52-week low ₹3,288.1052-week high ₹4,440.00
- Sector
- Engineering and construction
What happened
- DVC CIL Power, a 50:50 joint venture of Damodar Valley Corporation and Coal India, gave L&T Energy CarbonLite Solutions a limited notice to proceed (LNTP) for the main plant package of the Chandrapura thermal project, according to Upstox and Indian Masterminds.
- The project has two ultra-supercritical units of 800 MW each, 1,600 MW in total.
- The scope covers design, engineering, manufacturing, supply, erection, testing and commissioning of boilers, steam turbines, generators and electrostatic precipitators, with related mechanical, electrical, control and civil works.
- Upstox reported the order value as up to ₹10,000 crore. It said the formal notice to proceed follows environmental clearances.
- The shares closed at ₹3,692.00, down 2.07%.
Why it matters
Good to know: A limited notice to proceed lets work start on a defined part of a contract before every condition is met. The full notice to proceed comes later.
Key facts
- Client
- DVC CIL Power (Damodar Valley Corporation and Coal India)
- Project
- Chandrapura, Jharkhand: 2 × 800 MW
- Order value (Upstox)
- Up to ₹10,000 crore
Read the source
This is a summary of public news about Larsen & Toubro, for information only. It is not a recommendation to buy, sell or hold LT.
Larsen & Toubro in the news before
- 28 OCT 2026 · EVENING · RESULTSL&T's Q2 profit rises 33% to ₹5,202 crore; order book reaches ₹8,53,514 crore
- 6 OCT 2026 · EVENING · ORDERSL&T's power transmission arm wins 'mega' orders in Saudi Arabia, the UAE and India